Irrigation Engineering [1]
121) The height of dowel above the road level should not
be more than
-
(a) 10 cm
-
(b) 20 cm
-
(c) 30 cm
-
(d) 40 cm
122) The width of dowel is, usually, kept from
-
(a) 0.1 m to 0.3 m
-
(b) 0.3 m to 0.6 m
-
(c) 0.6 m to 0.9 m
-
(d) 0.9 m to 1.2 m
123) A spoil bank is formed when the
-
(a) canal has steep bed slope
-
(b) canal section is too large
-
(c) volume of excavation is in excess of the embankment filling
-
(d) canal alignment is meandrous
124) The borrow pits should, preferably, be taken from
-
(a) the field on the right side of canal
-
(b) the field on the left side of the canal
-
(c) the central half width of the section of the canal
-
(d) any one of the above
125) In case of small channels, the borrow pits should start
from a distance not less than ................. from the toe
of the embankment.
-
(a) 2 m
-
(b) 3 m
-
(c) 4 m
-
(d) 5 m